HARMON DEN – The N.C. Department of Transportation has raised its estimated cost to reconstruct Interstate 40 through the Pigeon River Gorge to approximately $2.8 billion and now expects to restore four lanes by late 2029.
The estimate is up from approximately $2 billion earlier in 2026, an increase of about $800 million. NCDOT said the figures remain subject to refinement as design and construction advance.
Hurricane Helene destroyed or severely damaged approximately five miles of I-40 in North Carolina through the gorge. NCDOT calls the work the largest reconstruction project in department history.
New geotechnical testing from river elevation found that bedrock is more than 50 feet below the surface in some locations. Reaching the deeper bedrock requires longer steel piles, which NCDOT said increased both the estimated cost and the projected schedule.
The rebuilding plan includes roller-compacted concrete walls, interlocking pipe-pile walls and related elements intended to make the corridor more resilient to future extreme river conditions.
NCDOT is using a Construction Manager/General Contractor delivery method that allows design, engineering and construction to proceed at the same time. Ames Construction was selected through a competitive procurement and is providing input on constructability, pricing and scheduling.